Metro Istanbul was established under the title of Istanbul Ulasim.
First stage of M1 Yenikapi-Ataturk Airport-Kirazli Line is commissioned in between Kartaltepe-Kocatepe and Emniyet stations.
Aksaray-Kartaltepe-Kocatepe stations became operational with the commissioning of Aksaray Station of M1 Yenikapi-Ataturk Airport-Kirazli Line.
Connection in between Esenler and Kartaltepe-Kocatepe became operational on M1 Yenikapi-Ataturk Airport-Kirazli Line.
First stage of T1 Kabatas-Bagcilar Tram Line is commissioned in between Yusufpasa and Beyazit.
Beyazit-Sirkeci extension of T1 Kabatas-Bagcilar Tram Line is completed and services commenced in between Yusufpasa and Sirkeci .
Yusufpasa-Topkapi extension of T1 Kabatas-Bagcilar Tram Line is completed and services commenced in between Topkapi and Sirkeci.
TF1 Macka-Taskisla Cable Car Line is commissioned.
Kartaltepe/Kocatepe-Zeytinburnu extension of M1 Yenikapi-Ataturk Airport-Kirazli Line is commissioned.
Zeytinburnu-Bakirkoy/Incirli extension of M1 Yenikapi-Ataturk Airport-Kirazli Line is commissioned.
Second stage of T1 Kabatas-Bagcilar Tram Line in between Topkapi-Zeytinburnu is commissioned and services commenced in between Zeytinburnu and Sirkeci.
Aksaray-Yenibosna services commenced with the commissioning of Bakirkoy/Incirli-Yenibosna extension of M1 Yenikapi-Ataturk Airport-Kirazli Line.
Eminonu Station of T1 Kabatas Bagcilar Tram Line is commissioned and services commenced in between Zeytinburnu and Eminonu.
Bahcelievler Station of M1 Yenikapi-Ataturk Airport-Kirazli Line is commissioned.
First stage of M2 Yenikapi-Haciosman Metro Line is commissioned in between Taksim and Levent.
4.Levent Station of M2 Yenikapi-Haciosman Metro Line is commissioned and services commenced in between Taksim and 4.Levent.
Yenibosna-Ataturk Airport extension of M1 Yenikapi-Ataturk Airport-Kirazli Metro Line is commissioned and services commenced in between Aksaray and Ataturk Airport.
T3 Kadikoy-Moda Tram Line is commissioned.
Eminonu-Findikli extension of T1 Kabatas-Bagcilar Tram Line is commissioned.
TF2 Eyup-Piyer Loti Cable Car Line is commissioned.
F1 Taksim-Kabatas Funicular Line is commissioned.
Findikli-Kabatas extension of T1 Kabatas-Bagcilar Tram Line is commissioned and services commenced in between Zeytinburnu and Kabatas.
T2 Zeytinburnu-Bagcilar Tram Line is commissioned.
First stage of T4 Topkapi-Mescid-i Selam Tram Line in between Sehitlik and Mescid-i Selam stations is commissioned.
4.Levent-Ataturk Oto Sanayi and Taksim-Sishane extensions of M2 Yenikapi-Haciosman Metro Line is commissioned.
Second stage of T4 Topkapi-Mescid-i Selam Tram Line in between Sehitlik and Topkapi stations is commissioned.
First and second stages of M2 Yenikapi-Haciosman Metro Line are combined and uninterrupted services commenced in between Taksim and Ataturk Oto Sanayi.
Darussafaka Station of M2 Yenikapi-Haciosman Metro Line is commissioned.
Seyrantepe Station of M2 Yenikapi-Haciosman Metro Line is commissioned and shuttle services commenced in between Sanayi Mahallesi and Seyrantepe.
Platform structures of T2 Zeytinburnu-Bagcilar Tram Line are made suitable for low floored trams and T1 and T2 Lines are combined and formed T1-Kabatas-Bagcilar Line.
Haciosman Station of M2 Yenikapi-Haciosman Metro Line is commissioned.
Esenler Station is renovated within the context of M1B construction and recommissioned.
First stage of M4 Kadikoy-Tavsantepe Metro Line is completed and services commenced in between Kadikoy and Kartal.
M3 Kirazli-Basaksehir/Metrokent Metro Line and Shuttle Services in between İkitelli Sanayi and Olimpiyat are commissioned.
Otogar-Kirazli stage of M1 Yenikapi-Ataturk Airport-Kirazli Line is completed and the line is divided as M1A Yenikapi-Ataturk Airport Line and M1B Yenikapi-Kirazli Line
Ayrilik Cesmesi Station is constructed as a part of M4 Kadikoy-Tavsantepe Metro Line's first stage and commissioned at the same day with Marmaray.
Yenikapi and Halic stations of M2 Yenikapi-Haciosman Metro Line are commissioned.
Halic Metro Bridge which harbours Halic Station of 2 Yenikapi-Haciosman Metro Line is commissioned.
18 "Istanbul Tram" which are manufactured by Metro Istanbul, started their services at T4 Topkapi-Mescid-i Selam after a ceremony.
Vezneciler-Istanbul University Station of M2 Yenikapi-Haciosman Metro Line is commissioned.
Yenikapi Station is commissioned and commenced providing services to M1A Yenikapi-Ataturk Airport and M1B Yenikapi-Kirazli Metro Lines.
M6 Levent-Bogazici University/Hisarustu Metro Line is commissioned.
Corporate name changed to Metro Istanbul after serving as Istanbul Ulaşım for 28 years.
Second stage of M4 Kadikoy-Tavsantepe Metro Line is commissioned in between Kartal and Tavsantepe.
First stage of M5 Uskudar-Cekmekoy Metro Line is completed and services commenced in between Uskudar and Yamanevler.
Second stage of M5 Uskudar-Cekmekoy Metro Line is commissioned in between Yamanevler-Cekmekoy.
"Night Metro services" commenced on Friday, Saturday and Public Holiday nights on 6 of our metro lines (M1A - M1B - M2 - M4 - M5 - M6)
First stage of M7 Kabatas-Esenyurt Metro Line is completed and services commenced in between Mecidiyekoy and Mahmutbey.
First stage of T5 Eminonu-Alibeykoy Cep Otogari Tram Line is completed and services commenced in between Cibali and Alibeykoy Cep Otogari.
Rıza Paşa Station is added to on the T3 Kadıköy-Moda Tram Line between Moda and Mühürdar Stations, thus, the number of stations on the line is increased to 11.